Prime Contractor
For Prime Contractors, a Mechanics Lien must be filed within 180 days from the date when payment becomes delinquent for materials or labor provided on the project, and enforcement of the lien must take place within 180 days from the date the lien was filed.
Sub/Laborer
For Subcontractors and Laborers, a Mechanics Lien must be filed within 180 days from the date when payment becomes delinquent for materials or labor provided on the project, and enforcement of the lien must take place within 180 days from the date the lien was filed.
Supplier/Other
For Suppliers and Others, a Mechanics Lien must be filed within 180 days from the date when payment becomes delinquent for materials or labor provided on the project, and enforcement of the lien must take place within 180 days from the date the lien was filed.