Prime Contractor
For Prime Contractors, a Mechanics Lien is required to be filed within 90 days of the last day labor or materials were provided on a construction project. Enforcement of the lien must take place within 6 months of the liens’ filing date.
Sub/Laborer
For Subcontractors and Laborers, a Mechanics Lien is required to be filed within 90 days of the last day labor or materials were provided on a construction project. Enforcement of the lien must take place within 6 months of the liens’ filing date.
Supplier/Other
For Suppliers and Others, a Mechanics Lien is required to be filed within 90 days of the last day labor or materials were provided on a construction project. Enforcement of the lien must take place within 6 months of the liens’ filing date.