Sub/Laborer
For Subcontractors and Laborers, a Notice of lien rights is required to be served to the owner of the property before labor or materials were provided for a construction project. Also, a written account of all labor and materials provided for the project must be delivered to the owner of the property upon request or within 30 days.
Supplier/Other
For Suppliers and Others, a Notice of lien rights is required to be served to the owner of the property before labor or materials were provided for a construction project. Also, a written account of all labor and materials provided for the project must be delivered to the owner of the property upon request or within 30 days.