Prime Contractor
Â
For Prime Contractors, a Mechanics Lien must be filed within 4 months after the projects completion. Enforcement of the lien must take place within 2 years after the project is completed.
Sub/Laborer
Â
For Subcontractors and Laborers, they must provide a Notice of Intent to Lien within 90 days of the last day labor and or materials were provided. Once the notice is sent and received, the lien must be filed within 4 months after the projects completion. Enforcement of the lien must take place within 2 years after the project is completed.
Supplier/Other
Â
For Suppliers and Others, they must provide a Notice of Intent to Lien within 90 days of the last day labor and or materials were provided. Once the notice is sent and received, the lien must be filed within 4 months after the projects completion. Enforcement of the lien must take place within 2 years after the project is completed.