Prime Contractor
For Prime Contractors, a Mechanics Lien is required to be filed within 4 months after the last day services or materials were provided on a project. If only labor was provided on the project, the time to file a lien is 2 months after the last day on the project. Enforcement of the lien is required within 6 months after last providing services or materials on the project.
Sub/Laborer
For Subcontractors and Laborers, a Mechanics Lien is required to be filed within 4 months after the last day services or materials were provided on a project. If only labor was provided on the project, the time to file a lien is 2 months after the last day on the project. Enforcement of the lien is required within 6 months after last providing services or materials on the project.
Supplier/Other
For Suppliers and Others, a Mechanics Lien is required to be filed within 4 months after the last day services or materials were provided on a project. If only labor was provided on the project, the time to file a lien is 2 months after the last day on the project. Enforcement of the lien is required within 6 months after last providing services or materials on the project.