Prime Contractor
For Prime Contractors, a Mechanics Lien must be filed within 120 days after last providing materials or labor for a construction project. Enforcement of the lien is limited to the 120 days after labor or materials were provided for a construction project.
Sub/Laborer
For Subcontractors and Laborers, a Mechanics Lien must be filed within 90 days after the last day materials or labor were provided for a construction project. Enforcement of the lien is limited to the 120 days after labor or materials were provided for a construction project.
Supplier/Other
For Suppliers and Others, a Mechanics Lien must be filed within 90 days after the last day materials or labor were provided for a construction project. Enforcement of the lien is limited to the 120 days after labor or materials were provided for a construction project.